A 1920s Cashmere villa master ensuite, slow-built

Stripped a clumsy 1990s ensuite back to the original timber and rebuilt it as architecture. Custom joinery, hand-glazed tile, deliberate slow build over four months.

Scope

Full reno

Region

Christchurch

Weeks on site

14

Total NZD

$118k

Phillipa and Andrew didn't want their bathroom finished quickly. They wanted it finished well. We worked one job at a time at Cashmere, and the brief — slow-built, considered, architectural — was the easy bit. Sourcing the hand-glazed Spanish terracotta tile took fourteen weeks alone.

We took the clumsy 1990s plasterboard back to the original 1920s framing and rebuilt with sympathetic joinery: a freestanding stone basin on a custom kauri vanity, a polished concrete shower base, and brushed brass everywhere brass would have been in 1925.

The build itself ran fourteen weeks on site. A finished bathroom this considered takes the time it takes.

Scope notes

  • Strip-out to original 1920s framing
  • Architectural drawings & PS1 documentation
  • Custom kauri vanity, hand-built
  • Polished concrete shower base
  • Hand-glazed Spanish terracotta wall tile
  • Brass tapware (Brodware Manhattan)
  • Sympathetic 1920s joinery profiles

Notable fixtures

  • Brodware Manhattan brass tapware
  • Custom kauri vanity, project-specific
  • Hand-glazed terracotta wall tile (imported)
  • Polished concrete shower base, in-situ poured

CCC building consent, eight weeks to issue.

Built by

Cashmere Bath Studio

Design-led, slow-build, architectural finish

Design-led studio for considered, slow-built renovations.

Full layout / structural · 7 yrs trading